KLIA Runway 3 resumes full operations ahead of schedule

Improvement works for Runway 3 at KLIA were originally set to end on March 17. (Youtube pic)

PETALING JAYA: Runway 3 at KLIA has resumed full-length operations seven days ahead of schedule after improvement works were completed earlier than planned.

In a Facebook post, KLIA said improvement works began with a full closure from Feb 24 to Feb 26, followed by operations under a shortened configuration while the remaining works continued.

“With the works now completed earlier than planned, the runway has resumed full-length operations ahead of schedule,” it said.

The operator said the works were part of ongoing efforts to maintain safety and quality standards.

The runway had been scheduled to re-open on March 17.